Report comment

Mine activity in the Pine Cove Pit finished in the middle of March, and the Company has commenced planning for pushbacks for the Pine Cove Pond and the North West Extension to the pit, which are expected to contribute ore in 2019. The Company is now converting the Pine Cove Pit into a fully-permitted in-pit tailings storage facility, which has approximately 15 years of capacity based on a throughput rate of 1,350 tonnes per day. Anaconda expects to begin tailings deposition in the third quarter of 2018.